Customise consent preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorised as "necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site.... 

Always active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Back to projects

The Old Admiralty Building

Location

The Mall

Sector

government

Nature

cut & carve and abestos removal

Value

£ 26 million

Employer

UK Department for Education

Delivered by

de-construct logo

Project details

The Old Admiralty Building is the new London Headquarters of the Department for International Trade, located in the heart of Whitehall on Horse Guards Parade. It was originally one of the buildings from which the worldwide affairs of the Royal Navy were run.

Deconstruct were commissioned to carry out extensive structural alterations and asbestos removal within the listed structures. The buildings were constructed in 3 phases from around 1900-1912, and are traditionally built with masonry, concrete and steel frames. Modernisation of the extensive space requires significant structural alteration.

Scope of works

  • removal of asbestos from within the fabric of the structure while introducing significant amounts of new structural openings
  • lift cores, external plant structures and structural framing within lightwells
  • significant temporary works and new structural steel, all of which designed by our in-house team.

Project constraints

Deconstruct have faced various challenges on this project, none less so than the way information was compiled during the 3-phase construction. Piecing this information together has required significant collaboration with the design team, Deconstruct have carried out an investigation across the building to verify what the professional team is expecting to uncover. This investigation has not only been to verify structure but to also identify where asbestos is present and provide a comprehensive report throughout the building, for the Department of Education to remain compliant following our departure.

With a programme spread over 100 weeks, this project demands a resource of over 150 operatives at its peak, covering asbestos removal, temporary works, demolition, steelwork installation, finishing concrete, making goods and heritage protection.

 